Title:
|
Resolution 19-05: (1) Approve and Authorize a Budget of $262,000 for the Design Phase of the Outer Harbor Intermodal Terminal (“OHIT”) Phase 2 - Interim Use Yard Paving Project and Authorize the Executive Director to Utilize WSP USA, Inc. for the Design Effort; and (2) Authorize the Executive Director to Utilize O.C. Jones & Sons, Inc. in the Not-To-Exceed amount of $446,700 for the Former Oakland Army Base Trench Spoils Off-Haul Project and Approve and Authorize the Executive Director to Delegate the Authority to the Director of Engineering to Approve the Project Manual, Plans, and Specifications for this Project. (Engineering/Maritime)
|