Title:
|
Resolution 19-42: (1) Approve a Budget of $3,477,000 for Design and Construction of the Terminal Flooring Replacement Project; (2) Authorize the Executive Director to Execute a Change Order with Turner Construction for Construction Manager at Risk (CM@R) Construction Services for a Guaranteed Maximum Price of $2,904,000 for the Terminal Flooring Replacement Project. (Aviation/Engineering)
|